Updates

alex cox-cuzzi
Jun 7, 2019

Thank You and Grand Opening Party

On behalf of the B.B. Italia & B.B. Pizza team, I would like to thank all of you for supporting our project! Working on this project with my brother, Daniel, is very special to me and we are grateful to be able to launch these two concepts and continue the legacy of a family-owned, neighborhood restaurant.

It is with great pleasure and excitement that I announce that we have officially opened our doors to the public! With that being said, the Grand Opening Party exclusively for NextSeed investors holding the bonus reward will be on Tuesday, June 11th. Qualifying investors should have received an invite from us. We hope to see you there! 

To view our hours and menus, please visit: http://www.bbitaliakitchen.com/

On behalf of the B.B. Italia & B.B. Pizza team, I would like to thank all of you for supporting our project! Working on this project with my brother, Daniel, is very special to me and we are grateful to be able to launch these two concepts and continue the legacy of a family-owned, neighborhood restaurant.

It is with great pleasure and excitement that I announce that we have officially opened our doors to the public! With that being said, the Grand Opening Party exclusively for NextSeed investors holding the bonus reward will be on Tuesday, June 11th. Qualifying investors should have received an invite from us. We hope to see you there! 

To view our hours and menus, please visit: http://www.bbitaliakitchen.com/

Read Less
B.B. Italia & B.B. Pizza (formerly Carmelo's)
Apr 8, 2019

Construction is moving forward & currently on schedule!

Heading into our last month of construction, we are on schedule to open for business on Thursday, May 2nd provided there are no unexpected catastrophes!

Exterior

Currently on the exterior:

  • We have completed the lower level of brick and are beginning the installation of the thin brick on the parapet.
  • Applying stucco to the soffit and the rear exterior walls.
  • Canopy has been framed out with the gutter installed and tied into the main system, the lights have been run and the paneling has been installed on top.
  • Steel plates with the logos cut out will be installed next on all three sides followed by the red LED lights and the soffit.
  • Patio planters will arrive early next week along with the steel gates and
Read More

Heading into our last month of construction, we are on schedule to open for business on Thursday, May 2nd provided there are no unexpected catastrophes!

Exterior

Currently on the exterior:

  • We have completed the lower level of brick and are beginning the installation of the thin brick on the parapet.
  • Applying stucco to the soffit and the rear exterior walls.
  • Canopy has been framed out with the gutter installed and tied into the main system, the lights have been run and the paneling has been installed on top.
  • Steel plates with the logos cut out will be installed next on all three sides followed by the red LED lights and the soffit.
  • Patio planters will arrive early next week along with the steel gates and the exterior brick will get painted white in two weeks.
  • Exterior signage should arrive by April 11th.

Interior

The interior is also moving quickly:

  • Sheet rock ceiling installation commenced today and the main dining room is near complete.
    • Once the sheet rock on the ceiling is completed and painted, the light fixtures will be installed. We are shooting for next Wednesday for that installation to begin. It should only take two days.
  • Tile in the bathroom floors is done and the walls will be completed imminently.
    • Bathrooms should be completely finished shortly.
  • All of the interior walls will be finished by the end of the week with wainscoting and anaglypta along with the floors.
  • Bar equipment and bar top will arrive sometime next week and all trades are on schedule to final out within the next couple of weeks.